Ex 5.3
Ex 5.3, 1 (ii)
Ex 5.3, 1 (iii) Important
Ex 5.3, 1 (iv)
Ex 5.3, 2 (i)
Ex 5.3, 2 (ii)
Ex 5.3, 2 (iii) Important
Ex 5.3, 3 (i)
Ex 5.3, 3 (ii)
Ex 5.3, 3 (iii)
Ex 5.3, 3 (iv) Important
Ex 5.3, 3 (v)
Ex 5.3, 3 (vi) Important
Ex 5.3, 3 (vii)
Ex 5.3, 3 (viii) Important
Ex 5.3, 3 (ix)
Ex 5.3, 3 (x)
Ex 5.3, 4
Ex 5.3, 5
Ex 5.3, 6 Important
Ex 5.3, 7
Ex 5.3, 8
Ex 5.3, 9
Ex 5.3, 10 (i)
Ex 5.3, 10 (ii) Important
Ex 5.3, 11 Important
Ex 5.3, 12
Ex 5.3, 13
Ex 5.3, 14 Important
Ex 5.3, 15 You are here
Ex 5.3, 16 Important
Ex 5.3, 17
Ex 5.3, 18 Important
Ex 5.3, 19 Important
Ex 5.3, 20 Important
Last updated at April 16, 2024 by Teachoo
You saved atleast 2 minutes by viewing the ad-free version of this page. Thank you for being a part of Teachoo Black.
Ex 5.3, 15 A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs. 200 for the first day, Rs. 250 for the second day, Rs. 300 for the third day, etc., the penalty for each succeeding day being Rs. 50 more than for the preceding day. How much money the contractor has to pay as penalty, if he has delayed the work by 30 days. Penalty for 1st day = 200 Penalty for 2nd day = 250 Penalty for 3rd day = 300 Hence, the series is 200, 250, 300, …. Since difference is same, it is AP Common difference = d = 50 We need to find total penalty if work is delayed by 30 days i.e. we need to find S30 We know that Sn = 𝒏/𝟐 (2a + (n – 1) d) Putting n = 30, a = 200 , d = 50 = 30/2 (2 × 200 + (30 − 1) × 50) = 15 (400 + 1450) = 15 × 1850 = 27750 Hence, total penalty if work is delayed by 30 days is Rs 27750