This question was asked in Ex 12.1, 1
A factory make tennis rackets and cricket bats.A tennis racket tacks 1.5 hours of machine time and 3 hours of craftsman time in it making while a cricket bat takes 3 hours of machine time and 1 hours of craftsman time.In a day the factory has the availability of not more then 42 hours of machine time and 24 hours of craftsman time.