Ex 11.2, 6 - A contractor estimates that 3 persons could rewire - Ex 11.2

part 2 - Ex 11.2, 6 - Ex 11.2 - Serial order wise - Chapter 11 Class 8 Direct and Inverse Proportions

Remove Ads

Transcript

Ex 11.2, 6 A contractor estimates that 3 persons could rewire Jasminder’s house in 4 days. If, he uses 4 persons instead of three, how long should they take to complete the job?Given, 3 persons can rewire the house in 4 days We need to find how many days would it take if number of workers is 4 Let the number of days be y Thus, our table looks like As we increase the number of persons, time taken would decrease ∴ They are in inverse proportion 3 × 4 = 3 × 𝒚 (3 × 4)/3 = 𝑦 4 = 𝑦 𝒚 = 4 ∴ It would require 4 days to complete the job

Davneet Singh's photo - Co-founder, Teachoo

Made by

Davneet Singh

Davneet Singh is an IIT Kanpur graduate and has been teaching for 16+ years. At Teachoo, he breaks down Maths, Science and Computer Science into simple steps so students understand concepts deeply and score with confidence.

Many students prefer Teachoo Black for a smooth, ad-free learning experience.