How much work is done in moving a charge of 2 C across two points having a potential difference 12 V?


Transcript

Example 12.2 How much work is done in moving a charge of 2 C across two points having a potential difference 12 V? Charge = Q = 2 C Potential difference = V = 12 V We need to find work done (W) We know that, Potential Difference = (π‘Šπ‘œπ‘Ÿπ‘˜ π‘‘π‘œπ‘›π‘’)/πΆβ„Žπ‘Žπ‘Ÿπ‘”π‘’ V = π‘Š/𝑄 VQ = W W = VQ W = 12 Γ— 2 W = 24 J Work done is 24 J